The Gümüşköy Geothermal Power Plant ((トルコ語:Gümüşköy Jeotermal Elektrik Santralı)) is an air-cooled Organic Ranking Cycle (ORC) system geothermal power plant located at Gümüşköy village of Germencik district in Aydın Province, Turkey.〔〔〔 The power plant feeds from the 182 °C Gümüşköy Geothermal Reservoir, which was discovered with the GK-1 geothermal well in October 2008.〔 The power plant has a gross installed power capacity of 13.20 MW divided in two units and uses two TAS Energy Inc., USA manufactured units for energy generation. Annual production is 108.24 GWh gross. The systems also feeds a purification and production plant having a 12-ton daily production capacity.〔〔 ==Gümüşköy Geothermal Reservoir== The Gümüşköy Geothermal Reservoir was discovered by BM Geothermal Group in 2008, as the first private sector high enthalpy geothermal discovery in Turkey. The reservoir is a lithologically capped hydrothermal system with three layers of reservoirs underlying one another. The first reservoir is located between 100- and 400-meter depths, with an average temperature of 100 °C. The second (interim) reservoir is located between 800- and 1400-meter depths, with an average temperature of 150 °C. The final reservoir is located around 2,000-meter depths with an average temperature of 180 °C.〔 The Gümüşköy Geothermal Power Plant produces from and re-injects into the interim and the bottom reservoirs. 抄文引用元・出典: フリー百科事典『 ウィキペディア(Wikipedia)』 ■ウィキペディアで「Gümüşköy Geothermal Power Plant」の詳細全文を読む スポンサード リンク
|